Lynker Presents Independent Study of Pebble Mine Dam Failure

On Friday, March 1st, Dr. Cameron Wobus presented findings to the Commercial Fisherman for Bristol Bay from a Pebble Mine Tailings Dam Failure analysis that was conducted by Lynker. The study was developed after report scoping documents indicated there was likely to be inadequate tailings dam failure scenarios considered in the Army Corps of Engineers Draft Environmental Impact Statement. In all scenarios analyzed by Lynker, a tailings dam failure would directly impact hundreds of miles of anadromous waters.

Hydrologist Dr. Cameron Wobus is a broadly trained earth scientist with approximately 15 years of experience in geomorphology, hydrology, and environmental data analysis and modeling.

 

Dr. Wobus’ complete presentation can be found here. The Commercial Fisherman for Bristol Bay have also posted a recording of the presentation.